Critical
2
act before the next planning cycle
Serious
5
schedule this quarter
Warning
4
fix when the record is next touched
Note
1
no action forced
What was read
- Materials
- 42
- Plants
- 3
- Suppliers
- 15
- Finished goods
- 9
- Purchase orders
- 46
- Customer orders
- 23
- Committed value
- Rp 18,214,000,000
- Rows in total
- 334
Critical (2)
Material with one source and committed revenue behind it
Rp 17,904,000,000continuity
14 material(s) have exactly one supplier on record and no alternate. Each is a single point of failure that stays invisible until the supplier misses. The figure beside this is the revenue that touches those materials, not an expected loss: one missed delivery does not stop every product that happens to contain the part.
Evidence (14)
- M-1124
- M-1130
- M-1136
- M-1142
- M-1148
- M-1160
- M-1172
- M-1196
- M-2222
- M-2228
- M-5512
- M-6648
- M-9910
- M-9922
Recommended. Qualify a second source, starting with the highest committed value.
Cover below the safety floor
Rp 3,515,000,000continuity
3 material and plant pair(s) hold less than 14 days of cover. The thinnest is M-4471 at KRW1 at 9.1 days.
Evidence (3)
- M-5512 at KRW1
- M-8830 at KRW1
- M-4471 at KRW1
Recommended. Bring supply forward or pre-position stock from another plant.
Serious (5)
Inbound lane concentrated on one port
Rp 14,924,000,000concentration
13 of 35 purchased materials route through CNNGB, which is 37% of the inbound book. One closure takes out all of them on the same day.
Evidence (12)
- M-1118
- M-1124
- M-1166
- M-1196
- M-1202
- M-2210
- M-3308
- M-4471
- M-4472
- M-5512
- M-6648
- M-7716
Recommended. Split the lane, or hold buffer on the far side of the chokepoint.
Bill of materials names a component that is not stocked anywhere
Rp 2,174,000,000integrity
1 component(s) appear in a product structure but have no stock record at any plant. Planning cannot see them, so a shortage will surface as a line stoppage rather than as a warning.
Evidence (1)
- M-1208
Recommended. Create the stock record, or remove the line if the component is obsolete.
Order past its delivery date and still not shipped
integrity
1 order(s) are overdue with no shipment recorded. Either the goods moved and nobody updated the record, or they did not move and nobody noticed.
Evidence (1)
- 4500018640
Recommended. Chase the supplier and reconcile the status before planning trusts it.
One supplier carries more than one code
integrity
1 supplier(s) appear under multiple codes. Spend is split across them, so the firm looks smaller than it is, concentration is understated, and a single certificate lapse hits more materials than the records suggest.
Evidence (2)
- SUP-4417
- SUP-4417B
Recommended. Merge the duplicates and repoint open orders at the surviving code.
Sourcing options in the file would worsen local content
compliance
3 option(s) would drop the local-content ratio below the current 38.2%, against a contract floor of 40.0%. The cheapest of them, Cheapest source in China, is Rp 48,000,000, which is exactly the trade a cost-only model would take.
Evidence (3)
- D
- E
- G
Recommended. Keep the veto ahead of the cost comparison, not after it.
Warning (4)
Customer order for a product with no bill of materials
Rp 310,000,000integrity
1 finished good(s) are being sold with no component structure behind them. Nothing can trace a disruption from a raw material to these orders.
Evidence (1)
- FG-9099
Recommended. Build the structure, or confirm the product is bought in finished.
Revised delivery date falls before the date originally promised
integrity
1 order(s) were revised earlier than the commitment. Either the supplier genuinely pulled the date in, or the revision overwrote the original. Every lead-time figure computed from this field inherits the error.
Evidence (1)
- 4500019204
Recommended. Confirm with the supplier, and keep the original commitment in its own field.
Material with one source and no traceable revenue
continuity
13 single-sourced material(s) could not be priced, because no bill of materials links them to a customer order. Unpriced is not the same as unimportant; it means the records do not say.
Evidence (13)
- M-1105
- M-1112
- M-1166
- M-1202
- M-2210
- M-2216
- M-3308
- M-3320
- M-5524
- M-5530
- M-6640
- M-7716
- M-7722
Recommended. Complete the product structure before judging whether these matter.
Stock held against a material nobody consumes
capital
1 position(s) carry stock with a consumption rate of zero. Either the rate is missing from the record or the stock is dead and tying up capital and floor space.
Evidence (1)
- M-1202 at CKR1
Recommended. Confirm the rate, then write off or redeploy what is genuinely dead.
Note (1)
Purchase order for a quantity of zero
integrity
2 order line(s) commit to nothing. Harmless individually, and a sign that order entry accepts input it should reject.
Evidence (2)
- 4500018946
- 4500019310
Recommended. Void the line and add a minimum-quantity check at entry.
Where the data came from
An audit that does not say which of its inputs were modelled is an audit of nothing. The weakest input here is modelled, and every conclusion above inherits that.
- MaterialStockmodelled · fixture:MaterialStock
- PurchaseOrdermodelled · fixture:PurchaseOrder
- BillOfMaterialmodelled · fixture:BillOfMaterial
- SalesOrdermodelled · fixture:SalesOrder
- AlternateSourcemodelled · fixture:AlternateSource
- Suppliermodelled · fixture:Supplier
- Quotationmodelled · fixture:Quotation
Every finding is computed from the rows named beside it. No model was involved, so any of it can be recomputed from the same file.