Agent team
Da

Dara

Demand

Owns the demand side. Daily consumption is a variable that moves, not a fixed number.

Tools 3 of 3

  • get_demand_signal

    Customer demand changes not yet reflected in the production schedule.

  • get_production_schedule

    Production schedule and daily consumption rate for one material at one plant.

  • forecast_demand

    Forecast daily consumption for a material at a plant from its withdrawal history, with a prediction interval. Compares the result against the planned rate in master data, which is the figure every cover date in the system is currently divided by. Deterministic: Holt's linear trend over a deseasonalised series, no model. Refuses when the history is too short to say anything.

Reasoning effort
medium
Instructions
written
Used in
0 runs

M-4471 at KRW1, daily withdrawals

The dashed rule is the planned 9.2 TON a day that every cover date in the system is divided by. The band is drawn from an in-sample error of 17.5%, so treat anything past today as an estimate rather than a plan.

modelled · fixture:MaterialStock
  • Daily withdrawn
  • 7-day mean
  • Forecast
  • 90% range
  • Planned 9.2 TON/day
051015209 Aug16 Aug23 Aug30 Aug6 Sept13 Sept20 Sept27 SepttodayTON

TON/day · 28 days observed, 30 forecast

show the numbers as a table
DateForecast TONLowHigh
2026-09-0410.3310.1510.51
2026-09-0510.3810.0310.72
2026-09-0610.3710.0110.73
2026-09-0710.429.6611.18
2026-09-0810.629.4211.82
2026-09-0910.658.9812.32
2026-09-1010.588.4112.75
2026-09-1110.68.113.1
2026-09-1210.617.9313.3
2026-09-1310.617.9213.31
2026-09-1410.647.6813.6
2026-09-1510.667.4613.86
2026-09-1610.687.2614.11
2026-09-1710.77.0814.33
2026-09-1810.726.9114.54
2026-09-1910.746.814.67
2026-09-2010.746.814.68
2026-09-2110.766.6414.89
2026-09-2210.796.4815.09
2026-09-2310.816.3415.28
2026-09-2410.836.215.46
2026-09-2510.856.0715.63
2026-09-2610.865.9915.73
2026-09-2710.865.9915.74
2026-09-2810.895.8615.91
2026-09-2910.915.7416.08
2026-09-3010.935.6216.24
2026-10-0110.955.5116.4
2026-10-0210.975.4116.55
2026-10-0310.995.3416.64

Planned rate against what actually happened

Every cover date in this system divides stock by the planned rate. 5 of 53 material and plant pairs ran at least 5% away from it over the last 28 days, so those cover dates are wrong. Drift compares what was actually withdrawn against the plan; the last column is where the forecast expects it to go next.

modelled · fixture:MaterialStock53 rows
MaterialPlantPlanned/dayLast 28dDrift %Next 30d
M-4471KRW19.210.3312.310.76
M-4471SBY19.610.6110.510.74
M-5518SBY11210.85-9.610.61
M-3308CKR1565.6599.596631.35
M-3308KRW1635.6669.195.3690.37
M-5512CKR12.92.993.12.92
M-3320CKR1131134.462.6134.12
M-1124KRW1103.1105.482.3108.65
M-4478KRW111.711.952.113.05
M-5524KRW13.33.23-2.12.91
M-1172SBY1532.8521.64-2.1507.56
M-1184KRW1699.2686.05-1.9703.53
M-5512KRW16.46.511.76.61
M-7710CKR1257.6261.981.7256.8
M-8836SBY145.646.351.647.12
M-2222KRW1230.1226.56-1.5224.17
M-1130CKR1650.8640.73-1.5658.3
M-6640CKR122.823.11.324.47
M-7716SBY1100.699.3-1.389.38
M-1118CKR170.469.52-1.366.2
M-9910KRW132.632.94130.56
M-1178CKR1877.8886.631900.14
M-1112KRW16362.44-0.965.15
M-3312CKR1694.5700.30.8734.68
M-9922CKR1548.8544.48-0.8541.43
M-1148SBY1437.9441.50.8442.09
M-5530CKR17.37.25-0.76.75
M-1190CKR1894888.07-0.7930.49
M-1136KRW1688.1691.390.5689.48
M-1142KRW1798.3794.21-0.5768.7
M-1166SBY1589.9586.72-0.5571.98
M-1196SBY1674670.54-0.5699.59
M-7722KRW191.591.16-0.489.37
M-8842SBY126.226.30.425.93
M-2210KRW1350.8349.54-0.4354.01
M-2216KRW19.39.26-0.49.24
M-4472SBY16.96.920.37.32
M-7710SBY1262.4263.250.3276.91
M-8830KRW17171.220.367.45
M-2216CKR18.68.57-0.38.07
M-1154SBY1322.3321.33-0.3311.26
M-1160KRW1664.8663-0.3633.96
M-1184SBY1237237.820.3221.39
M-1202CKR1279.3280.130.3273.24
M-1202CKR10280.130.3273.24
M-6648CKR1845.6844.28-0.2855.28
M-2228KRW145.745.63-0.243.48
M-1148CKR1442.7443.630.2427.03
M-9916KRW1395.3395.530.1397.72
M-1105KRW110.710.710.110.16
M-4472KRW16.46.406.25
M-8830SBY175.775.69072.76
M-1118SBY1527.1526.990537.01