Ve
Vega
Risk ScannerPrevent mode: hunts risk that has not happened yet. Single sources, concentrated lanes, certificates about to lapse.
Tools 2 of 2
scan_supply_exposure
Scan for risk that has not happened yet: materials with a single source, lanes concentrated on one port, and cover falling below policy inside the horizon. Ranked by the committed customer value behind each material. Deterministic.
get_supplier_certifications
A supplier's TKDN certificate and its validity dates. A certificate that lapses drops the local-content ratio with no physical event at all.
- Reasoning effort
- medium
- Instructions
- written
- Used in
- 1 runs
Latent risk
78 exposures across 53 material and plant pairs. 37 could not be priced: no bill of materials links them to a customer order, so the ranking puts them last rather than at zero.
modelled ยท scan over stock and purchase orders78 rows
| Exposure | Material | Why | At risk | Recommended | Needs |
|---|---|---|---|---|---|
| lane concentration | M-1118, M-1124, M-1166, M-1196, M-1202, M-2210, M-3308, M-4471, M-4472, M-5512, M-6648, M-7716, M-9910 | 13 materials route through CNNGB. One closure takes out all of them at once | Rp 14,924,000,000 | split the lane or hold buffer at the far side | draft for procurement |
| lane concentration | M-1105, M-1118, M-1142, M-1160, M-5518, M-7710, M-8830, M-9916 | 8 materials route through JPYOK. One closure takes out all of them at once | Rp 14,069,000,000 | split the lane or hold buffer at the far side | draft for procurement |
| lane concentration | M-1130, M-1136, M-1172, M-1184, M-2228, M-3320, M-4472, M-9922 | 8 materials route through IDTPP. One closure takes out all of them at once | Rp 9,853,000,000 | split the lane or hold buffer at the far side | draft for procurement |
| lane concentration | M-1148, M-2222, M-5524, M-7722, M-8830 | 5 materials route through THLCH. One closure takes out all of them at once | Rp 9,323,000,000 | split the lane or hold buffer at the far side | draft for procurement |
| single source | M-1124 | SUP-5501 is the only supplier on record, and no alternate source exists | Rp 5,864,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1124 | 22.0 days of cover, horizon is 56 days | Rp 5,864,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1148 | SUP-8801 is the only supplier on record, and no alternate source exists | Rp 5,864,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1148 | 35.0 days of cover, horizon is 56 days | Rp 5,864,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1148 | SUP-8801 is the only supplier on record, and no alternate source exists | Rp 5,864,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1148 | 22.0 days of cover, horizon is 56 days | Rp 5,864,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1130 | SUP-4431 is the only supplier on record, and no alternate source exists | Rp 5,642,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1130 | 44.0 days of cover, horizon is 56 days | Rp 5,642,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1142 | SUP-6622 is the only supplier on record, and no alternate source exists | Rp 4,746,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1142 | 28.0 days of cover, horizon is 56 days | Rp 4,746,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-9910 | SUP-2201 is the only supplier on record, and no alternate source exists | Rp 4,314,000,000 | qualify a second supplier | draft for procurement |
| single source | M-5512 | SUP-2209 is the only supplier on record, and no alternate source exists | Rp 3,515,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-5512 | 35.0 days of cover, horizon is 56 days | Rp 3,515,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-5512 | SUP-2209 is the only supplier on record, and no alternate source exists | Rp 3,515,000,000 | qualify a second supplier | draft for procurement |
| cover below policy | M-5512 | 13.0 days of cover against a 14 day floor | Rp 3,515,000,000 | pre-position stock or bring supply forward | autonomous under Rp 50 million |
| single source | M-6648 | SUP-2207 is the only supplier on record, and no alternate source exists | Rp 3,515,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-6648 | 18.0 days of cover, horizon is 56 days | Rp 3,515,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-1118 | 28.0 days of cover, horizon is 56 days | Rp 3,502,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-1178 | 28.0 days of cover, horizon is 56 days | Rp 3,502,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-2222 | SUP-8801 is the only supplier on record, and no alternate source exists | Rp 3,459,000,000 | qualify a second supplier | draft for procurement |
| single source | M-1160 | SUP-6610 is the only supplier on record, and no alternate source exists | Rp 2,362,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1160 | 44.0 days of cover, horizon is 56 days | Rp 2,362,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-7710 | 44.0 days of cover, horizon is 56 days | Rp 2,174,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-7710 | 22.0 days of cover, horizon is 56 days | Rp 2,174,000,000 | confirm inbound supply covers the gap | autonomous |
| lane concentration | M-1184, M-5530, M-7710, M-9916 | 4 materials route through MYPKG. One closure takes out all of them at once | Rp 2,174,000,000 | split the lane or hold buffer at the far side | draft for procurement |
| single source | M-2228 | SUP-4455 is the only supplier on record, and no alternate source exists | Rp 2,140,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-2228 | 28.0 days of cover, horizon is 56 days | Rp 2,140,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-4478 | 18.0 days of cover, horizon is 56 days | Rp 1,695,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1172 | SUP-4455 is the only supplier on record, and no alternate source exists | Rp 1,695,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1172 | 18.0 days of cover, horizon is 56 days | Rp 1,695,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-5518 | 35.0 days of cover, horizon is 56 days | Rp 1,285,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1136 | SUP-4455 is the only supplier on record, and no alternate source exists | Rp 1,285,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-8836 | 28.0 days of cover, horizon is 56 days | Rp 1,231,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-9922 | SUP-4455 is the only supplier on record, and no alternate source exists | Rp 1,231,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-9922 | 18.0 days of cover, horizon is 56 days | Rp 1,231,000,000 | confirm inbound supply covers the gap | autonomous |
| single source | M-1196 | SUP-2201 is the only supplier on record, and no alternate source exists | Rp 1,231,000,000 | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1196 | 22.0 days of cover, horizon is 56 days | Rp 1,231,000,000 | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-4471 | 18.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-5524 | SUP-8801 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-5524 | 35.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-5530 | SUP-8815 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| single source | M-3308 | SUP-2207 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-3308 | 18.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-3308 | SUP-2207 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| single source | M-3320 | SUP-4455 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-3320 | 35.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-6640 | SUP-3390 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-6640 | 44.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-7716 | SUP-2209 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| single source | M-7722 | SUP-8801 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-7722 | 44.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-8830 | 35.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| cover below policy | M-8830 | 13.0 days of cover against a 14 day floor | - | pre-position stock or bring supply forward | autonomous under Rp 50 million |
| cover runs out inside the horizon | M-8842 | 44.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-9916 | 28.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-2210 | SUP-2244 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-2210 | 44.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-2216 | SUP-3402 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-2216 | 18.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-2216 | SUP-3402 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-2216 | 18.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-1105 | SUP-6610 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1105 | 22.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-1112 | SUP-7701 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1112 | 22.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-1166 | SUP-2209 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover runs out inside the horizon | M-1166 | 18.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-1184 | 44.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| cover runs out inside the horizon | M-1190 | 35.0 days of cover, horizon is 56 days | - | confirm inbound supply covers the gap | autonomous |
| single source | M-1202 | SUP-5501 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| single source | M-1202 | SUP-5501 is the only supplier on record, and no alternate source exists | - | qualify a second supplier | draft for procurement |
| cover below policy | M-4471 | 9.1 days of cover against a 14 day floor | - | pre-position stock or bring supply forward | autonomous under Rp 50 million |
| lane concentration | M-2216, M-6640 | 2 materials route through VNSGN. One closure takes out all of them at once | - | split the lane or hold buffer at the far side | draft for procurement |
| lane concentration | M-1112, M-4471 | 2 materials route through KRPUS. One closure takes out all of them at once | - | split the lane or hold buffer at the far side | draft for procurement |